/images/product_buttons/MissingImage_button.gif/images/southwire_100x70.jpgDirect Current Field TestDirectCurrentFieldTest.htm
ENU
Register Now Forgot Password?

Direct Current Field Test

DIRECT CURRENT FIELD TESTS

  • LOW VOLTAGE NON-SHIELDED CABLES: "HI-POT" Test
  • LOW VOLTAGE NON-SHIELDED CABLES: "MEGGER" Test
  • IEEE 400: IEEE Guide for Making High-Direct-Current-Voltage Tests
  • AEIC CS-5-94: Cross-Linked Polyethylene Insulated Shielded Power Cables
  • AEIC CS-6-??: Ethylene Propylene Rubber Insulated Shielded Power Cables
  • Time-Leakage Test: Direct Current Time-Leakage Test


INTRODUCTION

SAFETY

Before conducting tests on a cable system, verify that the cable system is properly de-energized. If the system has been previously energized, follow the prescribed rules for switching necessary to de-energize, lockout, tag, and ground the cable system. The personnel conducting the testing must be qualified to operate the test equipment and be familiar with the cable system and its components.

PREPARATION FOR TESTING

Disconnect cables from non-cable system equipment and apparatus. This will reduce the possibility of erroneous test results. In the case of HVDC (High-Voltage-Direct-Current) testing, it will prevent damage to equipment and apparatus. Adequate physical clearances between the cable ends, and other equipment, other energized conductors, and to electrical ground must be checked. During the testing, be sure that unauthorized access to the cable system is maintained. Verify that proper procedures are taken to clear all tap(s) or lateral(s) in the circuit. Remove grounds from the cable phase to be tested. Phases not under test should remain grounded at all ends.

CONDUCTING TEST

Conduct test according to prescribed procedures and instructions. Record test results and retain for future reference.

 

--------------------------------------------------------------------------------

LOW VOLTAGE NON-SHIELDED CABLES

"HI-POT": High Voltage Potential DC Test

High potential tests are "go no-go" tests. The cable is required to withstand the specified voltage for the specified time duration. These tests will normally reveal gross imperfections due to improper field handling. Recommended test voltages are given in tables for dc and ac. Alternating current new installation test voltages are 80% of the factory test voltage. Direct current voltages are two times the ac new installation test voltage. Test duration should not exceed five minutes.

Recommended DC Dielectric Test Voltages For New Installations

Size

XHHW/RHH/RHW 

USE 

THHN/THWN 

14 

4800 

--- 

3200 

12

4800 

4800 

3200 

10 

4800 

4800 

3200 

8 - 2 

4800 

5600 

3200

1 - 4/0 

6400

6400

4000

250 -500 

8000

8000 

4800 

550 - 1000 

9600 

9600 

5600 

1100 - 2000

11200

11200 

6400 


Recommended AC Dielectric Test Voltages For New Installations

Size 

XHHW/RHH/RHW

USE 

THHN/THWN

 

 

 

 

14

2400 

--- 

1600

12 

2400

2400 

1600

10 

2400

2400 

1600

8-2 

2800 

2800 

1600 

1-4/0 

3200

3200 

2000 

250-500 

4000

4000 

2400 

550-1000 

4800 

4800 

2800 

1100-2000 

5600 

5600

3200 


--------------------------------------------------------------------------------

"MEGGER": Insulation Resistance Test

Low voltage, non-shielded cables can be tested using a battery powered ohmmeter or a device called a "megger". Hand held ohmmeters generally have outputs from several volts to 24 volts. They are excellent for detecting direct "shorts" such as bolted faults and low resistant measurements in the kilohm range. A "megger" measures resistance in the megohm range using higher voltages than an ohmmeter. Manual or motor-driven meggers are available for a range of fixed dc voltages. Typical fixed dc voltages are 500, 1000, 2500 and 5000 volts.

2 to 50 Megohm Rule
Applied dc potential may be 500 or 1000 volts dc with the insulation resistance reading taken at one minute. A megohm meter reading of less than 50 megohms may be used for deciding when to investigate the cable installation, readings less than two megohms will most likely indicate damaged insulation. Readings of 2 to 50 megohms are usually associated with long circuit lengths, moisture, or contamination. In most cases a 2 to 50 megohm reading does not indicate the insulation quality, therefore 2 to 50 megohms should not be specified as a pass/fail value. Insulation resistance readings should be made and interpreted by experienced testing specialists to determine the condition of the cable's insulation.

Note that it is difficult to obtain accurate insulation resistance measurements in the field. Factory tests are done in a controlled environment with the cable submerged in water to provide an electrical ground. Using factory test values are not recommended.

 

--------------------------------------------------------------------------------

MEDIUM VOLTAGE SHIELDED CABLES

IEEE 400

"IEEE Guide for Making High-Direct-Current-Voltage Tests on Power Cable Systems in the Field"

With any HVDC testing it is highly recommended that IEEE Standard 400 be understood and that there is concurrence of the manufacturers of the cables, terminals, and splices prior to the performance of any proposed testing. Table 1 is taken from IEEE Std. 400:

IEEE Standard 400 tests are "go no-go" tests. The system is required to withstand the specified voltage for the specified time duration. These tests will normally reveal gross imperfections due to improper field handling such as excessive bending or air gaps between the insulation and shield interfaces.

 

 

Table 1
Field Test Voltages for Shielded Power Cable Systems
5 kV to 35 kV

System 
Voltage
(kV rms)
phase-phase

System 
BIL
(kV)
(crest)
(cond-gnd)

Acceptance 
Test
Voltage*
(kV dc)
(cond-gnd)

Maintenance 
Test
Voltage**
(kV dc)

 

 

 

 

75

28 

23 

95 

36 

29 

15

110 

56 

46 

25 

150 

75 

61 

28 

170 

85 

68

35 

200

100 

75


* Acceptance test voltage duration is normally 15 minutes.
** Maintenance test voltage duration is normally not less than five minutes or more than 15 minutes.


--------------------------------------------------------------------------------

AEIC CS-5-94
"Specifications for Cross-Linked Polyethylene Insulated Shielded Power Cables Rated 5 Through 46 kV"


Tests During and After Installation
During Installation.
At any time during installation, a dc proof test may be made at a voltage not exceeding the dc test voltage specified for During Installation, applied for five consecutive minutes.
After installation. After the cable has been completely installed and placed in service, a dc proof test may be made at any time within the first five years at a voltage not exceeding the dc test voltage specified for the First five Years, applied for five consecutive minutes. After that time, dc testing is not recommended.
DC test voltages are applied to discover gross problems
such as improperly installed accessories or mechanical damage. DC testing is not expected to reveal deterioration due to aging in service. There is some evidence that dc testing of aged cross-linked polyethylene cables can lead to early cable failures.





Table 2
DC FIELD TEST VOLTAGES
Cross-Linked Polyethylene Insulated Shielded Power Cables


Rated Voltage During First Phase
to Phase (kV)

 

Insulation
Thickness

DC Test Voltages (kV)
During Installation
( 5 min)

First 5 years (5 min)

5

90 

28 

5 or 8 

115

36

11 

15 

175

56

18

15 

220

64

20

25

260

80

25

25

320

96

30

28

280

84

26

35

345

100

31

35

420

124

39

--------------------------------------------------------------------------------

AEIC CS-6-?? ---DO NOT SPECIFY COMPLIANCE---
"Specifications for Ethylene Propylene Rubber Insulated Shielded Power Cables Rated 5 Through 69 kV"

This information has not been adopted and is pending review by AEIC!

Tests During and After Installation

During Installation. At any time during installation, a dc proof test may be made at a voltage not exceeding the dc test voltage specified for During Installation, applied for five consecutive minutes.
After installation. After the cable has been completely installed and placed in service, a dc proof test may be made at any time within the first five years at a voltage not exceeding the dc test voltage specified for the First five Years, applied for five consecutive minutes.
DC test voltages are applied to discover gross problems such as improperly installed accessories or mechanical damage. DC testing is not expected to reveal deterioration due to aging in service.

This information has not been adopted and is pending review by AEIC!


Table 3
DC FIELD TEST VOLTAGES
Ethylene Propylene Rubber Insulated Shielded Power Cables

Rated Voltage Phase to
Phase (kV)

Insulation 
Thickness

DC test Voltages (kV)
During Installation (5 min)

First 5 years (5 min)

90

28

22

5 or 8 

115

36

29

15 

175

56

45

15

220

64

51

25

260

80

64

25

320

96

77

28

280

84

67

35

345

100

80

35

420

124

99

This information has not been adopted and is pending review by AEIC!

--------------------------------------------------------------------------------

Time-Leakage Test

For more sophisticated evaluations, it is important to recognize the components of dc "leakage" current. The output current of the test set into the cable is not the true leakage current. The output current is the sum of three currents; geometric capacitance, absorption, and true leakage current. The absolute value of output current is not of primary importance. This value is virtually impossible to predict and is dependent upon the previously mentioned factors which can affect the resultant output current from a few microamperes to hundreds of microamperes.

Time-Leakage Test, Components of DC Test Output Current (Diagram not available)

It is the shape of the total current curve (it) with respect to time that indicates the condition of the dielectric. A drop-off of current with respect to time is an indication of sound insulation. A rising current is an indication of questionable condition or impending failure. A flat curve is generally due to test conditions.

The output current variation with respect to time of voltage application is generally considered more indicative than the absolute value. The characteristic shapes of the time-leakage current curve and probable causes are outlined below.

1. A rising leakage curve at a steady voltage may be indicative of faulty insulation. However, other leakage paths (over porcelain surfaces and through insulating fluids) can contribute to such a result.

2. A falling leakage curve is indicative of good insulation characteristics, especially if at similar levels for all phases.

3. A flat leakage curve at low value is generally indicative of acceptable insulation. Flatness may be influenced by circuit length, cable geometry, and possible presence of moisture or contaminants over terminal surfaces.

4. A flat leakage curve at high value may indicate any of the following conditions:

a. presence of moisture
b. contaminants over terminal surfaces or other creepage surfaces
c. surface leakage greater than volume leakage
d. moist laminated insulation
e. condition of insulating fluids
f. air ionization losses (corona) from projections

5. Dissimilar leakage curves are indicative of nonuniformity of circuit insulation. The characteristic curve of each phase should be analyzed to determine the cause of dissimilarity. Air ionization losses from projections may affect one phase more than the others, dependent upon corona shielding (such as at terminals), temperature and humidity transients, air movement, and the like.

Generally speaking, the increase of current with test voltage is approximately linear for sound insulation. Care should be exercised to prevent terminal corona and minimize terminal surface leakage as these can mask test results.